Housing Developments

Masonbrook Holdings – Brocan Wood Monasterevin & Leinster Square Kildare

Client: Masonbrook
Site Location: Brocan Wood, Monasterevin
Description: Site Development consisting of Bulk Excavation, Foul & Surface Water Drainage, Laying Watermain; Ducting for Service, Kerbing, Footpaths, Public Lighting, Construction of Pumping Station

Glenveagh Homes – Kilbelin Newbridge & Grange Kilkenny

Project: Cluain Glasan & Belin Woods
Client/Developer: Glenveagh Homes Limited
Site Location: Grange Road Co. Kilkenny & Newbridge Co. Kildare
Description: Glenveagh Homes Limited, Subcontractor (Site Development Works Package): Killeen Civil Engineering

Killeen Civil Engineering was engaged by Glenveagh Homes, Developer, to undertake site development package works to both Cluain Glasan and Belin Woods. Cluain Glasan is 148 units of new residential homes, in Grange Road, Co. Kilkenny and Belin Woods is 343 units of new residential homes, in Newbridge, Co. Kildare.

This includes Demolition, Excavation & Earthworks, Road works, Cycle path & Footpath, Storm & Foul Water Drainage Network, Foul Pump Station, Watermain supply, Electrical supply ducting, Communication supply ducting, Substructure works, retaining walls, Public Road Realignment works and Landscaping.

 

Cairn Homes – Elsmore, Naas

Project Name:  Elsmore
Client/Developer: Cairn Construction Ltd
Site Location: Jigginstown, Naas 

Subcontractor Site Development Works Package: Killeen Civil Engineering 
Description: Killeen Civil Engineering was engaged by Cairn Construction Ltd, Developer, to undertake site development package works to Elsmore 250 units new residential homes. 

This contract included the provision of all of the infrastructure for the construction of 250 houses. The Link Road from Rathasker Road to O’Devoy Park was part of the contract. The foul and surface water sewers were up to 6m deep in very poor ground conditions with the water table at approx 1.5m. Sheet piling was required. 

This contract also included the construction of 200m of box culvert to permanently divert the Rathasker River to facilitate construction. The work involved the construction of dams at the inlet and outlet to the culvert; over-pumping of water through settlement tanks into lagoons; the provision of booms and straw bales to act as filtration before discharge of water; excavation of bed and bank of river; provision of granular bed for culvert; placing of culvert and headwalls; placing of rock armour at inlet and outlet to culvert. Site services, kerbing, street lighting, footpaths and road surfacing were included. 

 

Cairn Homes – Elsmore, Oak Park & Whitethorn, Naas

Project Name: Oak Park
Client/Developer: Cairn Construction Ltd
Site Location: Craddockstown, Naas

Subcontractor Site Development Works Package: Killeen Civil Engineering 
Description: All associated groundworks for 200 houses from topsoil strip and foundation level through to floor slab, services, paving and topsoiling including 1.7km of internal roadways within the development.

The contract also included the construction of a 600m of a new link road from Rathasker Road to O’Devoy Park with associated cycleways, footpaths and services, a new signalised junction, a roundabout and secondary road spurs. Construction of over 4km of mainline drainage at depths of up to 6m in difficult ground conditions where the water table was only 1m below ground level. This resulted in most of the drainage being sheet piled. Mainline drainage had to pass beneath an existing stream which was of high importance to the fisheries. Diversion of a stream through 200m of a 2.4m x 1.5m box culvert. Large dewatering scheme with lagoons, settlement and filtration systems set up to treat the pumped water to comply with fisheries and environmental requirements with over 3k of HDPE water main installed to Irish Water specification. Diversion and undergrounding of existing ESB lines throughout the site. 

 

Carroll O'Keefe - Silverbrook

Client/Developer: Carroll O’Keeffe & Co Ltd
Site Location: Silverbrook, Tullamore
Description: Site Development consisting of Bulk Excavation, Foul & Surface Water Drainage, Laying Watermain; Ducting for Service, Kerbing, Footpaths, Public Lighting. Phase 1 started  January 2019 and we are currently on Phase 7.

Housing Site, Thomastown

Project Name: Thomastown
Site Location: Thomastown Kilkenny